Project Title: Emeryville Marina Breakwater Replacement
Owner: City of Emeryville
Prime: Vortex Marine Construction, Inc.
Location: Emeryville CA
Date: June 2006 to March 2007
Description:
Construction of new 1282 lineal foot presressed concrete breakwater with associated fishing pier, and removal of existing timber breakwater.
Contract Value: $5,148,000
   
Project Title: Berth 23-26 & 30 Wharf & Embankment Strengthening Program
Owner: Port of Oakland
Prime: Vortex Marine Construction, Inc.
Location: Oakland CA
Date: July 2005 to November 2006
Description:
Construction and strengthening of 2,820 lineal feet of concrete wharf, and 4,575 lineal feet of embankment strengthening through the underwater installation of steel sheet pile.
Contract Value: $20,300,000
   
Project Title: Rehabilitation and Construction of Piers 1.5, 3 & 5
Owner: San Francisco Waterfront Partners, LLP
Prime: S.J. Amoroso Construction, Inc.
Location: San Francisco CA
Date: June 2004 to September 2006
Description:
Construction of new and structural rehabilitation of 90 year old concrete pile supported piers and wharfs.
Contract Value: $12,500,000
   
Project Title: Repairs to North Cargo Piers and Asssociated Bulkheads
Owner: Canaveral Port Authority
Prime: Vortex Marine Construction, Inc.
Location: Port Canaveral FL
Date: August 2004 to November 2006
Description:
Large scale concrete repair of wharf structures and installation of cathodic protection system.
Contract Value: $6,437,000
   
Project Title: Port Fender Replacement — Berths 2, 3 & 5
Owner: Port of Pensacola
Prime: Vortex Marine Construction, Inc.
Location: Pensacola FL
Date: January 2006 to June 2006
Description:
Construction of 1225 lineal feet of heavy timber and driven steel pile fender system at 3 port wharves.
Contract Value: $1,718,000
   
Project Title: Pier 4 Fender Replacement Concord NWS
Owner: U.S. Navy
Prime: American Bridge Co.
Location: Concord CA
Date: June 2006
Description:
As marine subcontractor to American Bridge Company, on a task order as part of 5 year IDIQ-MACC Contract for New Construction and Maintenance of the US Navys West Coast Facilities, Vortex replaced the Pier 4 timber fender system at the Concord Naval Weapons Station.
Contract Value: $565,000
   
Project Title: Richmond Yacht Club Marina Replacement
Owner: Richmond Yacht Club
Prime: Vortex Marine Construction, Inc.
Location: Richmond CA
Date: April 2005 to December 2005
Description:
Construction of 62,720 square foot marina complex with driven concrete prestressed piles
Contract Value: $4,876,000
   
Project Title: New Carquinez Bridge
Owner: California Department of Transportation
Prime: FCI/Cleveland Bridge JV
Location: Crockett CA
Date: April 2000 to February 2004
Description:
Large diameter marine pile driving and marine support for major suspension bridge construction.
Contract Value: $14,650,000
   
Project Title: Walter F. George Lock, Powerhouse, & Spillway
Owner: U.S. Army Corps of Engineers
Prime: Treviicos/Rodio JV
Location: Ft. Gaines GA/AL
Date: January 2002 to April 2004
Project Description:
Marine and underwater construction/support of prototype cut-off wall upstream of dam face, passing through lock and sub-bottom retaining wall, and tying in to foundation of dam in over 100 feet of water.
Contract Value: $9,570,000
   
Project Title: Waterfront Rehabilitation at USCG Station San Diego
Owner: U.S. Coast Guard
Prime: Vortex Marine Construction, Inc.
Location: San Diego CA
Date: December 2003 to April 2004
Project Description:
Replacement of an active small boat dock system with concrete piling, floats, access trestle and aluminum gangways in secure and environmentally sensitive area.
Contract Value: $628,350
   
Project Title: China Basin Ferry Terminal
Owner: Port of San Francisco
Prime: Vortex Marine Construction, Inc.
Location: San Francisco CA
Date: January 2001 to November 2001
Project Description:
Design–Build construction of a new ferry terminal for the Pac Bell ballpark, including 2 steel terminal floats, with hydraulic ramp systems and utilities, a structural concrete terminal pier, steel access ramps and gateway.
Contract Value: $2,900,000
   
Project Title: Point Protrero Wharf Repair
Owner: Port of Richmond/Transdevelopment Group
Prime: Vortex Marine Construction, Inc.
Location: Richmond CA
Date: March 2010 to November 2010
Project Description:
Rehabilitation of WWII era marine terminal including reinforced shotcrete repair of concrete pier deck slab, structural strengthening of concrete beams, girders and piling, and new mooring and fender systems.
Contract Value: $3,100,000
   
Project Title: Waterfront Improvements at USCG Station Alameda
Owner: U.S. Coast Guard
Prime: Vortex Marine Construction, Inc.
Location: Alameda CA
Date: March 2007 to January 2008
Project Description:
Repair of damaged concrete pier and piling with installation of new fender, mooring, and cathotic protection systems. Installation of monopile mooring dolphin and mooring hardware.
Contract Value: $2,016,000
   
Project Title: Napa River Bridge Emergency Fender Repair
Owner: Cal-Trans District 4
Prime: Vortex Marine Construction, Inc.
Location: Napa CA
Date: September 2007 to March 2008
Project Description:
Emergency repair of ship–damaged timber fender system of bridge with reinforced plastic system.
Contract Value: $1,750,000
   
Project Title: Berth 211 Wharf Improvements
Owner: Port of Los Angeles
Prime: Vortex Marine Construction, Inc.
Location: Los Angeles CA
Date: September 2007 to June 2008
Project Description:
Removal of existing mooring dolphins and installation of 3 new concrete mooring dolphins, including fender and automatic mooring systems and walkways.
Contract Value: $2,606,000
   
Project Title: IDIQ/MACC Contract for New Construction and Renovation of Facilities
Owner: NAVFAC
Prime: American Bridge Co.
Location: CA, OR, & WA
Date: October 2003 to June 2008
Project Description:
Construction and renovation of US Navy waterfront facilities — U.S. West Coast.
Contract Value: 5YR — $50M
   
Project Title: Annual Maintenance Dredging and Berth Deepening
Owner: Port of Oakland
Prime: Vortex Marine Construction, Inc.
Location: Oakland CA
Date: July 2007 to June 2008
Project Description:
Maintenance dredging and berth deepening at Port's active marine terminals.
Contract Value: $1,800,000
   
Project Title: Pier 40 Structural Improvements
Owner: San Francisco Redevelopment Agency
Prime: BCCI Construction Co.
Location: San Francisco CA
Date: June 2008 to March 2009
Project Description:
Marine demolition and rehabilitation of concrete pier, including pile jacketing, structural concrete repair, crack and spall repair, and cast-in-place boardwalk.
Contract Value: $2,705,000
   
Project Title: Replacement of Anode Arrays Along BART Tube Alignment
Owner: Bay Area Rapid Transit District (BART)
Prime: Vortex Marine Construction, Inc.
Location: San Francisco — Oakland CA
Date: June 2008 to June 2009
Project Description:
Replacement of seafloor and sub-bottom cathodic anode arrays along the BART tube alignment in water depths > 100 feet.
Contract Value: $2,653,000
   
Project Title: Richmond Entrance Channel and Harbor Dredging
Owner: U.S. Army Corps of Engineers
Prime: Vortex Marine Construction, Inc.
Location: Richmond CA
Date: May 2009 to November 2009
Project Description:
Marine dredging of 240,000CY of material in entrance channel and harbor.
Contract Value: $5,865,000
   
Project Title: Sacramento River Bank Protection
Owner: U.S. Army Corps of Engineers
Prime: Hard Rock Construction
Location: Sacramento CA
Date: November 2009 to December 2009
Project Description:
Levee repairs and marine placement of armor rock.
Contract Value: $443,000
   
Project Title: Yerba Buena Island Wave Panel Breakwater Replacement
Owner: U.S. Coast Guard
Prime: Abide International
Location: San Francisco CA
Date: October 2009 to March 2010
Project Description:
Replacement of timber wave panel breakwater with precast concrete panels and steel H–pile breakwater wall around Coast Guard small boat harbor and haul–out facility.
Contract Value: $1,615,000
   
Project Title: Fire Boat Headquarters — Pier 22 1/2 Pier Strengthening
Owner: City & County of San Francisco
Prime: Cowhey Pacific Drilling
Location: San Francisco CA
Date: October 2009 to January 2011
Project Description:
Marine seismic retrofit of pier beneath active firehouse, including installation of new steel support structure.
Contract Value: $2,051,000
   
Project Title: Rock Placement Over High–Pressure Gas Line at Carquinez Straits
Owner: Kinder Morgan/Central States Underwater, Inc.
Prime: Vortex Marine Construction, Inc.
Location: Benicia CA
Date: November 2010
Project Description:
Protective placement of 1,700 tons of rock, in 60 feet of water, on a high&ndashpressure gas line crossing at Benicia–Martinez Bridge.
Contract Value: Confidential